Services
1. Full project
lifecycle QM Consulting
Ø
Client installing SAP Quality Management for
the first time
Ø
Or client adding major SAP Quality Management
functionality above the initial go-live (examples: Outbound Certificate of
Analysis, Vendor Evaluation, Quality Notifications (CAPA), Tooling Calibration
Schedules)
Ø
Full project life cycle:
1. Project
Preparation
2. Blueprint
3. Realization
4. Go-live
Prep
5. Go-live
Follow-up
Ø
Will use what ever project methodology is being
used on a project. Preference though is
to use SAP ASAP methodology.
Ø
Can work independently or with another SAP
Partner, in cases where there is a SAP Partner managing the overall project
2. Offsite
Support Agreement
Ø
Daily Issues Resolution
Ø
Gap Resolution
Ø
Perform weekly QM Health Checks
Ø
Answering QM functionality questions
Ø
Provide recommendations for improvements
Ø
Provide training materials when needed
Ø
Help map out future functionality
Ø
Provide Roll-out Support
Logistics:
o Arrive
on site on a Friday
o Meet
with key QA/QC personnel
o Meet
with SAP QM core team members
o Perform
an existing QM Module assessment
o Receive
a QA/QC tour
o Receive
a remote login to provide production support
o Establish
a Support Agreement with different levels of response time depending on need,
minimum 24 hour response
o Flat
monthly fee for set amount of hours of support
o Support
over those hours would be additional
3. Installed
(already live) QM Module Assessment
Ø
Conduct installed QM Module walkthrough
Ø
Conduct fit/gap analysis
Ø
Provide recommendations for improvements
Ø
Provide recommendations for future functionality
Ø
Provide assistance in developing Quality Roadmap
Ø
Provide QM Health Check report
Logistics:
o Arrive
on site on a Friday
o Meet
with key QA/QC personnel
o Meet
with SAP QM core team members
o Flat
fee for original Assessment
o Additional
fee for assisting with Quality Roadmap
4. Training
Ø
Help client develop a Training Plan
Ø
Help design client specific Training Materials
Ø
Provide Train the Trainer sessions
Ø
Help develop training client data load plan so
there is data available for training
Logistics:
o Arrive
on site on a Friday
o Meet
with key QA/QC personnel
o Meet
with SAP QM core team members
o Meet
with SAP Training Coordinator
o Flat
fee for each work
o Additional
fee for off site work
5. Go-live
Readiness QA
Ø
Review Blueprint Documents to compare to planned
SAP QM functionality
Ø
Review Test Scripts for thoroughness
Ø
Review Master Data Load plan
Ø
Review Functional Data Load Plan
Ø
Review QM Training Plan
Ø
Review QM Documentation
Ø
Review QM Configuration
Ø
Help with Go/No Go decision
Ø
Provide Go-Live Readiness Report
Logistics:
o
This can be conducted at various stages during
the project lifecycle. Examples: prior
to first test cycle, prior to integration test, few weeks before go-live
o Arrive
on site on a Friday
o Meet
with key QA/QC personnel
o Meet
with SAP QM core team members
o Flat
fee for Go-Live Readiness report
|